The bill of material contains information necessary to


A) place an order to replenish the item
B) calculate quantities on hand and on order
C) convert net requirements into higher level gross requirements
D) convert gross requirements into net requirements
E) convert (explode) net requirements at one level into gross requirements at the next level

F) None of the above
G) A) and B)

Correct Answer

verifed

verified

The minimum record accuracy required for successful MRP is approximately


A) lower than 90%
B) 90%
C) 95%
D) 97%
E) 99%

F) B) and E)
G) None of the above

Correct Answer

verifed

verified

The MPS calls for 50 units of Product A and 60 of B. There are currently 35 of Product B on hand. Each A requires 2 of Part C; each B requires 5 of C. There are 160 units of C available. a. Calculate the net requirements for B. b. Calculate the gross requirements for C. c. Calculate the net requirements for C.

Correct Answer

verifed

verified

(a) 60 - 35 = 25; (b...

View Answer

Which of the following regarding enterprise resource planning (ERP) is true?


A) It involves an ongoing process for implementation.
B) It can incorporate improved, reengineered "best processes."
C) It has a software database that is off-the-shelf coding.
D) ERP systems usually include MRP, financial and human resource information.
E) All of the above are true.

F) A) and E)
G) C) and D)

Correct Answer

verifed

verified

Which of the following statements regarding the gross material requirements plan is true?


A) It shows total demand for an item.
B) It shows when an item must be ordered from a supplier or when production must be started.
C) It combines a master production schedule with the time-phased schedule.
D) It requires several inputs, including an accurate bill of material.
E) All of the above are true.

F) B) and D)
G) A) and B)

Correct Answer

verifed

verified

Firms making many different final products use __________ to facilitate production scheduling.


A) planning bills
B) modular bills
C) phantom bills
D) overdue bills
E) none of the above

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

What is the "supermarket" as it is used in MRP? How does it alter the responsibility for dealing with lead-time offsets?

Correct Answer

verifed

verified

The supermarket concept applies when par...

View Answer

The following table is an example of a(n) The following table is an example of a(n)    A)  aggregate plan B)  load report C)  master production schedule D)  capacity plan E)  inventory record


A) aggregate plan
B) load report
C) master production schedule
D) capacity plan
E) inventory record

F) A) and E)
G) All of the above

Correct Answer

verifed

verified

The __________ technique may be applicable where a firm's parts and subassemblies are common to a variety of its products.

Correct Answer

verifed

verified

The __________ is the input to material requirements planning which lists the assemblies, subassemblies, parts, and raw materials needed to produce one unit of finished product.


A) bill of material
B) master production schedule
C) inventory records
D) assembly time chart
E) net requirements chart

F) A) and E)
G) D) and E)

Correct Answer

verifed

verified

In job shop (make-to-order) operations, the master production schedule is usually expressed in


A) end items
B) modules
C) kits
D) customer orders
E) warehouse orders

F) None of the above
G) A) and B)

Correct Answer

verifed

verified

Which of the following is false concerning enterprise resource planning (ERP) ?


A) It attempts to automate and integrate the majority of business processes.
B) It shares common data and practices across the enterprise.
C) It is inexpensive to implement.
D) It provides and accesses information in a real-time environment.
E) All of the above are true.

F) A) and C)
G) A) and B)

Correct Answer

verifed

verified

What does the part-period balancing lot-sizing technique attempt to do in deciding the lot sizes?

Correct Answer

verifed

verified

It balances the setup and hold...

View Answer

Capacity planning in closed-loop MRP


A) utilizes feedback about workload from each work center
B) may make use of resource requirements profiles (load reports)
C) may smooth work center loads with such tactics as overlapping and lot splitting
D) does not add capacity, but rather seeks effective use of existing capacity
E) All of the above are true.

F) A) and B)
G) B) and E)

Correct Answer

verifed

verified

Consider the following bill of material. Fifty units of Product A are needed. Assuming no on-hand inventory, and no scheduled receipts, explode the bill of material.

Correct Answer

verifed

verified

blured image Item A: 50 units; Item B: 50 ...

View Answer

Given the following bill of material Given the following bill of material   If the demand for product A is 30 units, and there are 10 units of B on hand and none of C, how many units of part D will be needed? A)  3 B)  40 C)  70 D)  90 E)  110 If the demand for product A is 30 units, and there are 10 units of B on hand and none of C, how many units of part D will be needed?


A) 3
B) 40
C) 70
D) 90
E) 110

F) B) and D)
G) B) and C)

Correct Answer

verifed

verified

Jacquie Welkener, operations manager for ABC Technologies, must schedule work for the next five days. Each unit takes 30 minutes to process. Available capacity is 8 hours per day. The production order quantities are 12, 18, 20, 13, and 17 for Monday through Friday, respectively. What should be the production plan?

Correct Answer

verifed

verified

Sixteen units should be produced each da...

View Answer

What does enterprise resource planning (ERP) allow an organization to do?

Correct Answer

verifed

verified

It allows them to automate and integrate...

View Answer

A process-focus facility (for example, a print shop) will likely schedule __________ as the focus of its master production schedule.

Correct Answer

verifed

verified

What is MRP? Identify four benefits from its use.

Correct Answer

verifed

verified

MRP or material requirements planning is...

View Answer

Showing 81 - 100 of 172

Related Exams

Show Answer