A) labor, material and equipment costs.
B) direct costs plus interest.
C) direct labor costs and the project manager's salary.
D) direct costs and the project manager's salary.
E) direct and indirect costs.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Multiple Choice
A) normal
B) crash
C) estimated
D) accelerated
E) completion
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) resources
B) budget
C) team morale
D) risk
E) customers
Correct Answer
verified
Multiple Choice
A) Incentive contracts
B) High network sensitivity
C) Imposed deadlines
D) High overhead costs
E) Unforeseen delays
Correct Answer
verified
Multiple Choice
A) Assign additional staff and equipment
B) Subcontract work
C) Schedule overtime
D) Outsource project work
E) Establish a core project team
Correct Answer
verified
Multiple Choice
A) Increased risk
B) Fatigue and resentment
C) Increased cost
D) Decrease in available management reserve
E) Reduced quality
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) A
B) B
C) C
D) D
E) E
Correct Answer
verified
Multiple Choice
A) network
B) critical path
C) project cost-duration
D) release burndown
E) risk breakdown
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) increased
B) decelerated
C) accelerated
D) compressed
E) reduced
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) less it costs to shorten one time period.
B) more it costs to shorten one time period.
C) smaller the crash time is.
D) larger the crash time is.
E) cannot be determined by the information given.
Correct Answer
verified
Multiple Choice
A) increase.
B) become unstable.
C) decrease.
D) become unreliable.
E) stay the same.
Correct Answer
verified
Multiple Choice
A) accumulated
B) total
C) budgeted
D) time-phased
E) estimated
Correct Answer
verified
Multiple Choice
A) Schedule risk
B) Project impact
C) Stakeholder impact
D) Customer impact
E) Inherent risk
Correct Answer
verified
Multiple Choice
A) $20
B) $30
C) $40
D) $50
E) $60
Correct Answer
verified
Showing 41 - 60 of 106
Related Exams