Correct Answer
verified
Multiple Choice
A) direct
B) budgeted
C) accumulated
D) indirect
E) time-phased
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) time-constrained
B) vision-limited
C) schedule-constrained
D) resource-constrained
E) physically-constrained
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) Find the activity with the lowest crash cost
B) Calculate the optimum cost-time point
C) Calculate the crash point
D) Calculate indirect cost per time unit
E) Find the activity with the steepest cost slope
Correct Answer
verified
Multiple Choice
A) direct
B) indirect
C) overhead
D) total
E) normal
Correct Answer
verified
True/False
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) involves crashing all activities to their crash point.
B) can only be done when resources are not constrained.
C) is always more expensive.
D) tends to increase network sensitivity.
E) should be considered for all projects.
Correct Answer
verified
Multiple Choice
A) importance
B) resources
C) duration
D) customer-perceived value
E) slope or crash cost per unit
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) nonlinear
B) additive
C) divisibility
D) linear
E) quadratic
Correct Answer
verified
Multiple Choice
A) shortest path
B) path with the greatest variability
C) critical path
D) path with the least amount of resources required
E) path with the most resources required
Correct Answer
verified
Multiple Choice
A) imposed project deadlines.
B) time to market.
C) unforeseen project delays.
D) high overhead.
E) incentive contracts.
Correct Answer
verified
Multiple Choice
A) (normal cost - crash cost) / (normal time - crash time)
B) (crash cost - normal cost) / (normal time - crash time)
C) (normal time - crash time) / (crash cost - normal cost)
D) (normal time - crash time) / (normal cost - crash cost)
E) (crash cost - normal cost) / (crash time - normal time)
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) linear.
B) curvilinear.
C) variable.
D) conversely related.
E) exponentially related.
Correct Answer
verified
Multiple Choice
A) direct costs are the lowest.
B) indirect costs are the lowest.
C) direct costs equal indirect costs.
D) total project costs are the lowest.
E) the project changes from time-constrained to resource-constrained.
Correct Answer
verified
True/False
Correct Answer
verified
Showing 81 - 100 of 106