One of the items included on a project scope statement or checklist is the acceptance criteria.

A) True
B) False

Correct Answer

verifed

verified

The intersection of work packages and the organizational unit creates a project control point called a(n) ___________.


A) deliverable
B) subdeliverable
C) work package
D) lowest subdeliverable
E) cost account

F) A) and D)
G) D) and E)

Correct Answer

verifed

verified

A robust ______________ can go a long way to reducing project problems over the life of the project and will establish how, when and to whom information must be supplied.


A) project charter
B) priorities matrix
C) requirements doc
D) communications plan
E) WBS

F) D) and E)
G) C) and D)

Correct Answer

verifed

verified

Identify the three categories used to classify the priority of major project parameters.

Correct Answer

verifed

verified

Accept (lo...

View Answer

What are the major causes of scope creep? What can the project manager do to minimize scope creep within each of these causes?

Correct Answer

verifed

verified

The major causes of scope creep are poor...

View Answer

What is a responsibility matrix and how would it be used in project management?

Correct Answer

verifed

verified

The responsibility matrix (RM) summarize...

View Answer

If a project criterion should be optimized if at all possible, it is classified as being constrained.

A) True
B) False

Correct Answer

verifed

verified

Scope creep can be reduced by carefully writing a(n) __________.


A) project charter
B) statement of work
C) requirements document
D) project plan
E) scope statement

F) A) and B)
G) All of the above

Correct Answer

verifed

verified

One of the primary jobs of a project manager is to manage the trade-offs among time, cost, and performance. To do so, the project manager must define and understand the ___________ of the project.


A) project charter
B) communications plan
C) priorities
D) requirements
E) WBS

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

During the course of a project, project priorities may change impacting the project priority matrix. Give an example.

Correct Answer

verifed

verified

The customer may suddenly need...

View Answer

The hierarchical work breakdown structure provides management with information appropriate to each level.

A) True
B) False

Correct Answer

verifed

verified

If the project scope needs to change, it is critical to have a sound _______ in place that records the change.


A) requirements document
B) project charter
C) change control process
D) WBS
E) statement of work

F) A) and E)
G) B) and E)

Correct Answer

verifed

verified

The agreement that training will be the responsibility of the customer and not the team is an example of a project ________.


A) product scope description
B) limits and exclusions
C) technical requirements
D) acceptance criteria
E) milestones

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

A communication plan is a key component for giving guidelines on how to track project ____.


A) issues.
B) costs.
C) defects.
D) Both costs and defects.
E) All of these choices are correct.

F) B) and D)
G) B) and C)

Correct Answer

verifed

verified

Responsibility matrices are used primarily with small and medium-sized projects and have limited use in large projects.

A) True
B) False

Correct Answer

verifed

verified

An expected output over the life of a project would be classified as


A) a target.
B) a product.
C) an end object.
D) a deliverable.
E) an objective.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

The highest element in the hierarchical breakdown of the WBS is the first major deliverable for the project and the lowest element is a work package.

A) True
B) False

Correct Answer

verifed

verified

Five steps are involved when defining a project. Which of the following is the first?


A) Establish project priorities
B) Define the project scope
C) Verify the budget available
D) Assign team members to work on the project
E) Determine the required completion date

F) B) and E)
G) None of the above

Correct Answer

verifed

verified

A communication plan should include limits on who has access to certain kinds of information.

A) True
B) False

Correct Answer

verifed

verified

There is a strong correlation between project success and clear project scope definition.

A) True
B) False

Correct Answer

verifed

verified