 The main tool for performing scope validation is _____ and group decision making techniques.

Correct Answer

verifed

verified

 Project scope management includes the processes involved in defining and controlling what is or is not included in a project.

A) True
B) False

Correct Answer

verifed

verified

 Mind mapping can be used for developing WBSs using which approach?


A) analogy approach only
B) bottom-up or analogy approach
C) top-down or bottom-up approach
D) any approach

E) A) and C)
F) None of the above

Correct Answer

verifed

verified

 A work package is a task at the _____ level of the WBS.

Correct Answer

verifed

verified

 Which action involves defining and documenting the features and functions of the products produced during the project as well as the processes used for creating them?


A) Collecting requirements
B) Defining scope
C) Controlling scope
D) Validating scope

E) C) and D)
F) B) and C)

Correct Answer

verifed

verified

 Given the project management software that is available, it is relatively easy to create a good WBS.

A) True
B) False

Correct Answer

verifed

verified

 When using project management software, estimates of work time should be entered only at the work package level; the rest of the WBS items are just groupings or _____ tasks.

Correct Answer

verifed

verified

 The format of the WBS dictionary is essentially the same for all projects.

A) True
B) False

Correct Answer

verifed

verified

 Some organizations prescribe the form and content for WBSs for particular projects. These are known as _____.

Correct Answer

verifed

verified

 A(n) _____ is a deliverable-oriented grouping of the work involved in a project that defines its total scope.

Correct Answer

verifed

verified

WBS
work b...

View Answer

 Which output documents how project needs will be analyzed, documented, and managed?


A) requirements traceability matrix
B) requirements management plan
C) WBS
D) project scope statement

E) None of the above
F) A) and D)

Correct Answer

verifed

verified

 A work package represents one component of the product that the project aims to deliver.

A) True
B) False

Correct Answer

verifed

verified

 What is scope creep?


A) the tendency for project scope to keep getting bigger and bigger
B) subdividing project deliverables into smaller pieces
C) the approved project scope statement and its associated WBS.
D) a task at the lowest level of the WBS

E) C) and D)
F) A) and B)

Correct Answer

verifed

verified

 Describe the process of scope validation.

Correct Answer

verifed

verified

Scope validation involves formal accepta...

View Answer

 Which action involves normalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables?


A) Creating scope
B) Defining scope
C) Controlling scope
D) Validating scope

E) A) and C)
F) All of the above

Correct Answer

verifed

verified

 A(n) _____ is a table that lists requirements, their various attributes, and the status of the requirements to ensure that all are addressed.

Correct Answer

verifed

verified

requirements traceab...

View Answer

 Which process involves identifying and modeling business events, who initiated them, and how the system should respond to them?


A) Prototyping
B) JAD
C) RAD
D) Use case modeling

E) B) and C)
F) All of the above

Correct Answer

verifed

verified

 _____ is the difference between planned and actual performance.

Correct Answer

verifed

verified

 Creating the WBS is a subprocess associated with which process in project scope management?


A) planning
B) monitoring and controlling
C) closing
D) executing

E) C) and D)
F) B) and D)

Correct Answer

verifed

verified

 What is a work breakdown structure? What are the inputs and tools used for creating one?

Correct Answer

verifed

verified

A work breakdown structure (WBS) is a de...

View Answer