A) the slope of the cml is (m- rrf) /bm.
B) all portfolios that lie on the cml to the right of σm are inefficient.
C) all portfolios that lie on the cml to the left of σm are inefficient.
D) the slope of the cml is (m - rrf) /σm.
E) the capital market line (cml) is a curved line that connects the risk-free rate and the market portfolio.
Correct Answer
verified
Multiple Choice
A) 11.69%; 1.22
B) 12.30%; 1.28
C) 12.92%; 1.34
D) 13.56%; 1.41
E) 14.24%; 1.48
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) 10.29%
B) 10.83%
C) 11.40%
D) 12.00%
E) 12.60%
Correct Answer
verified
Multiple Choice
A) 7.89
B) 8.30
C) 8.74
D) 9.20
E) 9.66
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) richard roll has argued that it is possible to test the capm to see if it is correct.
B) tests have shown that the risk/return relationship appears to be linear, but the slope of the relationship is greater than that predicted by the capm.
C) tests have shown that the betas of individual stocks are stable over time, but that the betas of large portfolios are much less stable.
D) the most widely cited study of the validity of the capm is one performed by modigliani and miller.
E) tests have shown that the betas of individual stocks are unstable over time, but that the betas of large portfolios are reasonably stable over time.
Correct Answer
verified
True/False
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Multiple Choice
A) standard deviation; correlation coefficient.
B) beta; variance.
C) coefficient of variation; beta.
D) beta; beta.
E) variance; correlation coefficient.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) sometimes, during a period when the company is undergoing a change such as toward more leverage or riskier assets, the calculated beta will be drastically different than the "true" or "expected future" beta.
B) the beta of "the market," can change over time, sometimes drastically.
C) sometimes the past data used to calculate beta do not reflect the likely risk of the firm for the future because conditions have changed.
D) there is a wide confidence interval around a typical stock's estimated beta.
E) sometimes a security or project does not have a past history which can be used as a basis for calculating beta.
Correct Answer
verified
Multiple Choice
A) the expected return on the investor's portfolio will probably have an expected return that is somewhat below 10% and a standard deviation (sd) of approximately 10%.
B) the expected return on the investor's portfolio will probably have an expected return that is somewhat below 15% and a standard deviation (sd) that is between 10% and 20%.
C) the investor's risk/return indifference curve will be tangent to the cml at a point where the expected return is in the range of 7% to 10%.
D) since the two stocks have a zero correlation coefficient, the investor can form a riskless portfolio whose expected return is in the range of 10% to 15%.
E) the expected return on the investor's portfolio will probably have an expected return that is somewhat above 15% and a standard deviation (sd) of approximately 20%.
Correct Answer
verified
Multiple Choice
A) stock b must be a more desirable addition to a portfolio than stock a.
B) stock a must be a more desirable addition to a portfolio than stock b.
C) the expected return on stock a should be greater than that on stock b.
D) the expected return on stock b should be greater than that on stock a.
E) when held in isolation, stock a has greater risk than stock b.
Correct Answer
verified
Showing 21 - 35 of 35
Related Exams