A) when each is taking vacation time or time off.
B) know the name of each resource on the project.
C) list all the projects to which the resources have been assigned.
D) indicate the amounts and types of resources needed to perform each activity.
Correct Answer
verified
Multiple Choice
A) 16 days, 7 workers
B) 7 days, 5 workers
C) 5 days, 7 workers
D) 8 days, 3 workers
Correct Answer
verified
Multiple Choice
A) schedule with a technical constraint.
B) schedule with a resource constraint.
C) level the costs of the project.
D) maintain a uniform level of required resources.
Correct Answer
verified
Multiple Choice
A) increase costs of all the activities in the project.
B) extend beyond the project completion time.
C) be completed ahead of schedule.
D) increase its requirements for additional resources for all activities.
Correct Answer
verified
Multiple Choice
A) on availability times.
B) an as-late-as-possible (ALAP) schedule.
C) on an as-soon-as-possible (ASAP) schedule.
D) on a limited schedule plan.
Correct Answer
verified
Multiple Choice
A) The activities using the limited resources are shown in a ladder relationship as they are available.
B) The activities using the limited resources are shown in a loop relationship as they are available.
C) The activities requiring the limited resource are assigned at different times.
D) If there is no technical constraint for the activities, the activities could be arranged serially by the availability of the resources.
Correct Answer
verified
Multiple Choice
A) Paths would be 1,2,3,5 and 1,2,4
B) Paths would be 1,2,3,4 and 1,2,5
C) Paths would be 1,2 and 3,4,5
D) Path would be 1,2,3,4,5
Correct Answer
verified
Multiple Choice
A) The activities use different resources.
B) The activities are independent of each other.
C) From a technical standpoint, the activities must be performed in that sequence.
D) The order of completion doesn't matter.
Correct Answer
verified
Multiple Choice
A) The delaying of activities increases the costs of the project.
B) The delaying of activities decreases the acceptance of the project deliverable.
C) The delaying of activities may delay the project.
D) The delaying of activities helps give others more time on their tasks because they won't affect the project schedule.
Correct Answer
verified
Multiple Choice
A) who is responsible for which activities.
B) the amount of labor expenses for the project.
C) the expected utilization of resources by time period during the time span of the project.
D) the budget for material and cost resources.
Correct Answer
verified
Multiple Choice
A) Activities that use the same resource may not be able to occur in parallel to each other.
B) Activities that use different resources may be shown in a serial relationship.
C) The activities could be shown in a loop relationship.
D) Resources that are unlimited are not shown in a resource assignment.
Correct Answer
verified
Multiple Choice
A) each of the activities are independent from the other activities.
B) one activity cannot be started until the predecessors are finished.
C) the activities use different resources to be completed.
D) some activities use the same resources that may not be available.
Correct Answer
verified
Multiple Choice
A)
B)
C)
D)
Correct Answer
verified
Multiple Choice
A) developing a schedule that attempts to minimize the fluctuations in requirements for resources.
B) making sure all the resources do the same amount of work.
C) making sure every task has the same number of resources.
D) developing the shortest schedule when the number or amount of available resources is fixed and cannot be exceeded.
Correct Answer
verified
Multiple Choice
A) the least slack have first priority.
B) the longest duration have first priority.
C) the near term have first priority.
D) use the most resources have first priority.
Correct Answer
verified
Multiple Choice
A) developing a schedule that attempts to minimize the fluctuations in requirements for resources.
B) making sure all the resources do the same amount of work.
C) making sure every task has the same number of resources.
D) extending the project to have the least number of resources used per day.
Correct Answer
verified
Multiple Choice
A) day 18
B) day 3
C) day 10
D) day 9
Correct Answer
verified
Multiple Choice
A) Project management information systems
B) Formulas and techniques
C) Trial and error techniques
D) Calendaring systems
Correct Answer
verified
Multiple Choice
A) equal number of resources is assigned to each task.
B) an equal number of tasks are completed each day by the resources on the project.
C) they are applied as uniformly as possible without extending the project schedule beyond the required completion time.
D) the costs for the resources are even as possible across the project.
Correct Answer
verified
Multiple Choice
A) on availability times.
B) an as-late-as-possible (ALAP) schedule.
C) on an as-soon-as-possible (ASAP) schedule.
D) on a limited schedule plan.
Correct Answer
verified
Showing 1 - 20 of 21