What is the process of tracing upward in the bill of material from the component to the parent item in order to determine the cause for the component requirement?


A) net requirements planning
B) time fencing
C) pegging
D) backtracking
E) leveling

F) B) and E)
G) B) and C)

Correct Answer

verifed

verified

What is MRP? Identify four benefits from its use.

Correct Answer

verifed

verified

MRP or material requirements planning is...

View Answer

Time fences divide that segment of the master schedule that can be revised from that section that is "not to be rescheduled."

A) True
B) False

Correct Answer

verifed

verified

Reduced inventory levels and faster response to market changes are both benefits of MRP.

A) True
B) False

Correct Answer

verifed

verified

In MRP,the number of units projected to be available at the beginning of each time period refers to:


A) net requirements.
B) scheduled receipts.
C) planned order releases.
D) projected on hand.
E) the amount necessary to cover a shortage.

F) C) and D)
G) A) and E)

Correct Answer

verifed

verified

Firms may discover that,rather than adapting ERP to the way they do business,they have to adapt the way they do business to accommodate the ERP software.

A) True
B) False

Correct Answer

verifed

verified

Explain what is meant by "nervousness" of the MRP schedule.Provide an example.Name two tools that are particularly useful in reducing system nervousness in MRP systems.

Correct Answer

verifed

verified

Nervousness is the reaction to a large n...

View Answer

Consider the following requirements for a certain product. Consider the following requirements for a certain product.    Beginning inventory = 500 units Setup cost = $500 per setup Lead time = 1 week Holding cost = $3 per unit per week a.Develop the lot-for-lot MRP table. b.Calculate the total relevant costs. Beginning inventory = 500 units Setup cost = $500 per setup Lead time = 1 week Holding cost = $3 per unit per week a.Develop the lot-for-lot MRP table. b.Calculate the total relevant costs.

Correct Answer

verifed

verified

There are three setups at $500 each,tota...

View Answer

What does enterprise resource planning (ERP)allow an organization to do?

Correct Answer

verifed

verified

It allows the organization to automate a...

View Answer

The minimum record accuracy required for successful MRP is approximately which of the following?


A) lower than 90%
B) 90%
C) 95%
D) 97%
E) 99%

F) A) and E)
G) C) and D)

Correct Answer

verifed

verified

A(n)________ can illustrate whether a work center has been scheduled beyond its capacity.

Correct Answer

verifed

verified

load repor...

View Answer

Which of the following best describes a gross material requirements plan?


A) a schedule that shows total demand for an item,and when it must be ordered from a supplier or when production must be started
B) an intermediate range plan for the scheduling of families of products
C) a chart illustrating whether capacity has been exceeded
D) a table that corrects scheduled quantities for inventory on hand
E) a schedule showing which products are to be manufactured and in what quantities

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

What do we mean by closed-loop MRP?

Correct Answer

verifed

verified

It's a system that provides fe...

View Answer